ANALISA PRODUKTIVITAS ALAT BERAT PADA PROYEK NORMALISASI BENDALI GANG KANTIL
Abstrak (Abstracts)
In the Bendali Gang Kantil Pos 10 Normalization Project, Balikpapan Baru, heavy equipment is needed to carry out excavation and dumping works. The purpose and objective of this project is to anticipate the excessive performance of the Bendali when the rainy season comes so that the Bendali can function optimally as a water control structure. In soil disposal work, the sedimentation is excavated using a long arm excavator then stacked on the side of the bend first so that the water content can be reduced then done using a standard arm excavator type heavy equipment which functions to load the sedimentation results which will be removed by the dump truck. In the work, the result of sedimentation is dumped in a designated place as far as 6.9 km. In this study, using the heavy equipment productivity method by processing data in the form of calculating the productivity of the tools, calculating the number of tools and the duration of work and calculating the cost of the work. Optimization of the work “Normalization Bendali Gang Kantil” can be done using alternative 2 with 2 units of long arm excavators for 16 hours of work, 1 unit of standard arm excavator for 112 hours of work and 8 units of dump trucks for 112 hours of work with a total work cost of Rp 130.112.283,04 Pada Proyek Normalisasi Bendali Gang Kantil Pos 10, Balikpapan Baru diperlukan alat berat untuk mengerjakan pekerjaan galian dan buangan. Maksud dan tujuan dari proyek ini adalah untuk mengantisipasi kinerja Bendali yang berlebihan ketika musim hujan datang sehingga bendali dapat berfungsi optimal sebagai bangunan pengendali air. Pada pekerjaan buangan tanah sedimentasi digali menggunakan excavator long arm kemudian ditumpuk di sisi bendali telebih dahulu agar kandungan air bisa berkurang kemudian dikerjakan menggunakan alat berat berjenis excavator standard arm yang berfungsi memuat hasil sedimentasi yang akan dibuang oleh dump truck. Pada pekerjaan buangan hasil sedimentasi dibuang di tempat yang telah ditentukan sejauh 6,9 km. Pada penelitian ini menggunakan metode produktivitas alat berat dengan melakukan pengolahan data berupa perhitungan produktivitas alat, perhitungan jumlah alat dan durasi pekerjaan serta perhitungan biaya pekerjaan. Optimalisasi pekerjaan “Normalisasi Bendali Gang Kantil” dapat dilakukan menggunakan alternatif 2 dengan 2 unit excavator long arm selama 16 jam kerja, excavator standard arm 1 unit selama 112 jam kerja dan dump truck 8 unit selama 112 jam kerja dengan total biaya pekerjaan sebesar Rp Rp 130.112.283,04

Keyword : Earth Moving, Productivity, Excavator, Dump Truck.

Nilai Properti
: ALWET EKO PRASETYO, : 922016035, : Politeknik Negeri Balikpapan, : TEKNIK SIPIL, : 2020, : Indonesia, : Tugas Akhir, : Prepustakaan Poltekba,

 

Download Full Text
Pembimbing
Rahmat Bangun Giarto, S.T., M.Eng.

E-mail :

www.poltekba.ac.id
Dr. Emil Azmanajaya, S.T., M.T.

E-mail :emil.azmanajaya@poltekba.ac.id

www.poltekba.ac.id
https://www.elementbike.id/data/selotgacorku/https://karanganbungacilacap.com/https://karanganbungacilacap.com/selotgacorku/https://sipolahta.dispermadesdukcapil.jatengprov.go.id/fontawesome-free/-/slot186/https://dupak.dinkes.jatimprov.go.id/public/storage/-/https://simawa.upnvj.ac.id/uploads/temp/smaxwin/https://e-learning.uniba-bpn.ac.id/rahasia/https://www.elementbike.id/product/slot186/https://bpiw.pu.go.id/image/scatter/http://lms.sipil.ft.unand.ac.id/layouts/https://e-learning.universitasbumigora.ac.id/local/maxclub/