Project’s Detail

DESKRIPSI TUGAS AKHIR :
PERENCANAAN STRUKTUR BAWAH MASJID AL-MUHANDIS POLITEKNIK NEGERI BALIKPAPAN
Abstrak (Abstracts)
During the procces of construction of the Al-Muhandis Mosque which was first carried out and worked on was a lower structure work. In analyzing the structure of the building must be designed to meet the requirements of stability, strength, and durability of the materials forming the structure to meet objectives such as the economy and the ease of implementation of the production of Al-Muhandis Mosque which was first carried out and worked on was a under structure work. The purpose of this research is to find out the dimensions of the footplate foundation which is determined by the carrying capacity of the permit on the ground where the foundation is placed. According to the results of the analysis of soil bearing capacity at each foundation point using the Terzaghi method yielding permit carrying capacity of: (P1) qall = 134,437 KN / m2 and (P2) qall = 159,193 KN / m2. The results of the analysis of local palm foundations with dimension plans (P1) = 1,5 m x 1,5 m and (P2) 2,00 m x 2,00 m are able to withstand both the one-way and two-way stresses and shear forces. Pada saat melaksanakan suatu pembangunan konstruksi Masjid Al-Muhandis yang pertama kali dilaksanakan dan dikerjakan adalah pekerjaan struktur bawah. Dalam menganalisa struktur bawah bangunan harus dirancang agar memenuhi syarat-syarat kestabilan, kekuatan, dan keawetan dari bahan-bahan pembentuk struktur untuk memenuhi tujuan-tujuan seperti ekonomi dan kemudahan dalam pelaksanaan. Tujuan dari penelitian ini adalah untuk mengetahui dimensi dari pondasi telapak yang di tentukan oleh kapasitas dukung ijin pada tanah dimana pondasi tersebut diletakkan. Menurut hasil analisis kapasitas dukung tanah pada masing-masing titik pondasi dengan menggunakan metode Terzaghi menghasilkan kapasitas dukung ijin sebesar: (P1) qall = 134,437 KN/m2 dan (P2) qall = 159,193 KN/m2. Adapun hasil analisa pondasi telapak setempat dengan rencana dimensi (P1) = 1,5 m x 1,5 m dan (P2) 2,00 m x 2,00 m mampu menahan tegangan dan gaya geser baik satu arah maupun dua arah.

Keyword : Foundation, SAP 2000, Kapasitas Dukung

Nilai Properti
: ROFIQOH, : 922016025, : Politeknik Negeri Balikpapan, : TEKNIK SIPIL, : 2019, : Indonesia, : Tugas Akhir, : Prepustakaan Poltekba,

 

Download Full Text
Pembimbing
Mersianty, S.T., M.T.

E-mail :mersianty@poltekba.ac.id

www.poltekba.ac.id
Ezra Hartarto Pongtuluran, S.T., M.Eng.

E-mail :

www.poltekba.ac.id
https://www.elementbike.id/data/selotgacorku/https://karanganbungacilacap.com/https://vclass.unila.ac.id/blog/sdana/https://sipolahta.dispermadesdukcapil.jatengprov.go.id/fontawesome-free/-/slot186/https://dupak.dinkes.jatimprov.go.id/public/storage/-/https://simawa.upnvj.ac.id/uploads/temp/smaxwin/https://e-learning.uniba-bpn.ac.id/rahasia/https://www.elementbike.id/product/slot186/https://bpiw.pu.go.id/image/scatter/http://lms.sipil.ft.unand.ac.id/layouts/https://e-learning.universitasbumigora.ac.id/local/maxclub/